Local Calumet weather
 

Click Here For Complete Weather
 

Keweenaw Commentary...See What Everyone’Äôs Talking About!!!!

Click Here For Keweenaw Today Click Here For Keweenaw CommentaryClick Here For Keweenaw Today

Document defends DEQ permit denial for Bete Grise South 

The Michigan Department of Environmental Quality has twice denied a permit to build a road that would access a potential residential development on this stretch of Lake Superior shoreline at Bete Grise South. (Keweenaw Today file photo) 

GRAND HAVEN ’Äì A document based on state and federal laws for protection of environmental and historic resources could, according to its author, settle the contested denial of a permit to build a road across a wetland at Bete Grise South, an area of Lake Superior shoreline on the east side of the Keweenaw Peninsula.

 

The document, a Motion for Summary Disposition, was filed on May 18, 2001, by intervenors in the case, who are supporting the decision of the Michigan Department of Environmental Quality (DEQ) to deny the permit to Lake Superior Land Company (LSLC), now a subsidiary of International Paper (IP). The intervenors ’Äì Mendota Lighthouse owner Gary Kohs and Timothy Bureau, author of the Motion and president of Resource Management Group, Inc., Environmental Planners & Consultants in Grand Haven, Mich. ’Äì claim LSLC did not meet statutory/administrative timelines and requirements in their appeal of the permit denial.

 

The DEQ Office of Administrative Hearings in Lansing ordered both parties in the case (LSLC and the DEQ Land and Water Management Division) to respond to the Motion by Friday, June 15. As of 3 p.m. on June 15, the Office of Administrative Hearings had not received any response ’Äì by fax or by mail ’Äì from either party. However, a response postmarked by June 15 would be acceptable, according to a representative of that office.

 

Neither the DEQ Land and Water Management Division nor LSLC/IP’Äôs Public Affairs Manager Mark Pontti would comment directly on the case, which is pending.

 

Pontti simply said, ’ÄúAs for Bete Grise South, we continue to evaluate our options.’Äù

 

Karl Weber of Plunkett and Cooney (Marquette), LSLC’Äôs attorney, said he intended to respond to the motion by the deadline but added he was not prepared to comment on the case. 

 

Harold Martin, assistant attorney general, who is defending the DEQ Land and Water Management Division in the case, said on June 8 that he expected to file a general agreement with the motion.

 

’ÄúI don’Äôt disagree with their motion. I’Äôm prepared to defend the DEQ’Äôs position,’Äù Martin said.

 

Since September 1999, the DEQ has twice denied LSLC a permit to build an access road through this wetland because of potential impacts to its ecosystem. LSLC has stated that the purpose of the road would be to access a proposed lakeshore residential development on about a mile of upland adjacent to the wetland and south of the Mendota Lighthouse.

 

After a public hearing in Mohawk on July 14, 1999, followed by a public comment period, the DEQ denied the permit application on September 3, 1999 ’Äì based on Part 301, Inland Lakes and Streams, and Part 303, Wetland Protection of the Natural Resources and Environmental Protection Act (NREPA), PA 451 of 1994, as amended. After LSLC provided the DEQ with additional information, including archaeological and plant studies, a second public hearing was held in Mohawk on May 1, 2000. The DEQ denied the permit a second time in July 2000. Officials of the DEQ Land and Water Management Division based their second denial mainly on impacts to the wetland hydrology and wildlife habitat. They also noted nearby alternative sites where the company could put the proposed development.


Timothy Bureau,  president of Resource Management Group, Inc., Environmental Planners & Consultants in Grand Haven, Mich., is an intervenor supporting the DEQ in an Administrative Law appeal by Lake Superior Land Co. of the DEQ's denial of a road permit at Bete Grise South. 

In September 2000, LSLC filed a petition for a DEQ Contested Case Hearing on the permit denial. Kohs and Bureau later applied to intervene in the case in support of the DEQ Land and Water Management Division. On May 18, 2001, Bureau submitted the Motion for Summary Disposition, based on five instances in which Petitioner LSLC did not meet statutory/administrative timelines and requirements after the first DEQ denial: 

        1)     The petitioner failed to file a State administrative appeal of the first DEQ denial within 60 days. The Motion demonstrates that the Sept. 3, 1999, denial letter from the DEQ to Don Schwandt, then LSLC president, includes a statement informing LSLC of that deadline. A Jan. 10, 2000, request under the Freedom of Information Act confirmed no appeal had been filed, Bureau notes in the Motion.

 

2)     The petitioner failed to appeal the finding of Coastal Zone Management inconsistency within 30 days. In order to support his claim of the importance of this deadline, Bureau includes in the Motion document an excerpt from the 1972 Coastal Zone Management Act (PL92-583) Rules. The DEQ letter of Sept. 3, 1999, states federal permits cannot be given because the project is inconsistent with the Michigan Coastal Management Program. Bureau concludes this situation made the project unlawful under Part 301 of NREPA, Section 30106, because of activities that would ’Äúunlawfully impair or destroy any of the waters or other natural resources of the state.’Äù He also concludes the project cannot be approved under Part 303 of NREPA, Section 30311 (1) ’Äúunless the department (DEQ) determines that the issuance of a permit is in the public interest ’Ķ’Äù

 

3)     The petitioner failed to respond to a Department request for further information within 30 days. Bureau’Äôs Motion includes a reply from Schwandt to the DEQ dated Sept. 9, 1999, in which LSLC acknowledged five types of additional information requested by the DEQ:

 

a.     a revised wetland delineation map;

b.     a biological survey of the project site documenting whether state-listed threatened, endangered or special concern plants would be impacted by the proposed development;

c.     an archaeological survey of the project site;

d.     a detailed plan to indicate how hydrology of the stream and wetland would be minimized with road construction methods (This plan was later questioned by professors of civil engineering at the second public hearing on May 1, 2000);

e.     a detailed wetland mitigation plan. 

Bureau notes Schwandt did not request additional time to produce the required information and, further, a DEQ response to his FOIA request confirmed at least 130 days elapsed without any documents being submitted to the DEQ. 

Said Bureau, whose FOIA request included phone calls, ’ÄúThey (LSLC) never even called to say it would take longer than 30 days to provide the information.’Äù 

4)     The project as proposed is unlawful under Section 106 of the National Historic Preservation Act of 1966, as amended. Bureau notes that the Mendota Lighthouse is eligible for listing in the National Register of Historic Places. He explains that the State Historic Preservation Officer (SHPO), in a Feb. 2, 2000, letter, specified that the surrounding land may only be developed if a certain set of conditions are met in order to protect the lighthouse and historic outbuildings. SHPO required that the United States Army Corps of Engineers agree to these conditions and execute the SHPO enforcement document before a permit could be granted. However, Bureau adds, the Army Corps is legally barred from entering into such an agreement.

 

’ÄúThus, the Contested Case Hearing process is moot and the conditions for approval from SHPO cannot be legally met,’Äù Bureau says in the Motion.

 

Furthermore, a 1983 Memorandum of Agreement between the State of Michigan and the United States Environmental Protection Agency (USEPA) requires the EPA be notified about sites identified or proposed under the national Historic Preservation Act. Bureau notes consultation with the USEPA has not been conducted.

 

5)     The petitioner did not submit a development plan for the property. Without this plan, since both existing and potential adverse environmental effects need to be determined, the department cannot issue a permit, Bureau states. Without a development plan, the DEQ is unable to determine the following:

 

a.     That adverse effects to the environment and the public trust are minimal and will be mitigated as much as possible.

b.     That the resource affected is not a rare resource. (The Nature Conservancy, or TNC, has identified this wetland site as a globally rare Great Lakes Marsh and as their number-one priority Keweenaw area for preservation. Tina Hall, TNC Upper  Peninsula conservation director, has said the conservancy would purchase the area to preserve its sensitive ecosystem if it were for sale at fair market value.)

c.     That the public interest in the proposed development is greater than the public interest in the unavoidable degradation of the resource.

d.     That no feasible and prudent alternative is available.

 

’ÄúThe denial stands,’Äù Bureau said this week in an explanation of the Motion for Summary Disposition. ’ÄúThey (LSLC) did not protect their rights. They did not exhaust their administrative remedies. Case closed.’Äù

 

Bureau repeated what he had stated at the May 1, 2000, public hearing in Mohawk, ’ÄúWe shouldn’Äôt even be here.’Äù

 

AWAKE Trustee Janet Avery of Gratiot Lake 

Janet Avery, trustee of AWAKE (Association Working Against Keweenaw Exploitation), said she believes the 60-day filing deadline is the most important of Bureau’Äôs points in the Motion.

 

’ÄúThey (LSLC) let it go,’Äù Avery said. ’ÄúThe other thing that is important is that we have not seen any plan for this housing development, which is a stated outcome of the road. That has always bothered us (AWAKE).’Äù

 

Besides AWAKE and The Nature Conservancy,  organizations that have opposed the permit for a potential road and development at Bete Grise South also include the Lake Superior Alliance, the National Wildlife Federation and FOLK (Friends of the Land of Keweenaw).

 

During the time period between the two DEQ permit denials, Schwandt disappeared from his position as president of LSLC.

 

A Jan. 12, 2000, article in The Daily Mining Gazette said former Lake Superior Land President Don Schwandt was no longer employed in that position. At that time, LSLC was a subsidiary of Champion International, which later merged with International Paper, Inc. Champion officials, the article noted, declined to say whether Schwandt had been fired or resigned. The article also cited Art Abramson, then general manager of Champion’Äôs Lake States Region forest resources (He now holds that position for IP) as saying development issues, such as the proposed development at Bete Grise, were not a factor in the Schwandt decision but were a company concern.

 

Bureau said neither the fact that Schwandt no longer held his LSLC position nor the merger of Champion with IP had any bearing on the facts presented in his Motion.

 

Bureau spoke at both public hearings on the Bete Grise issue, outlining how he believed the proposed road and development are in violation of both state and federal laws.

 

’ÄúWe intend to continue to fight to protect that area to the best of our ability,’Äù Bureau said this week.

 

Click here for Keweenaw Today’Äôs July 26, 2000, article, which gives more background on the Bete Grise issue, including statements made at that time by Tim Bureau and by Richard Gutleber, Army Corps spokesman in Marquette.

 

Click here to comment on this article ...

 

Click here for a printable, pdf version of this article. You will need Adobe Acrobat Reader, which you can easily download, at no cost, from the Internet.

 

                                                           ’Äì  Michele Anderson

                                                                                June 16, 2001