|
DEQ
addresses concerns prior to hearing on Mt. Bohemia
sewer permits
MARQUETTE ’Äì
At a public hearing concerning the proposed
lagoon and sewer treatment system for Mt. Bohemia,
Department of Environmental Quality officials will
provide handouts with a summary of questions and
responses on Black Bear Entertainment, Adventure
& Recreation Company’Äôs application for a Part
31 Groundwater Discharge Permit and a Pump &
Haul Permit. The informational handouts for the
public will also include MDEQ drafts of these
permits.
The hearing will begin at 7 p.m. Wednesday, Jan.
24, at the Mohawk School. DEQ Waste Management
Division staff from Marquette will be present:
Robert Schmeling, supervisor; Randy Conroy, senior
district geologist; Margie Ring, senior engineer;
and Karen Isaacson, secretary. Brian Brady,
multi-media coordinator, will conduct the hearing,
which will be tape-recorded.
Conroy said he believed the handouts could
satisfy some concerns and benefit the application
process. He noted significant questions and comments
brought up at the hearing or sent to the Department
before Jan. 31 (the end of the comment period) will
be added to the comments and response document and
made available upon request.
"We would respond in the format of this
document, and we would provide that to them,"
Conroy said.
UP Engineers and Architects submitted the draft
Irrigation Management Plan, or IMP, (for the planned
spray irrigation process of wastewater discharge),
on Jan. 9, 2001. The IMP was not complete when the
Part 31 application was turned in on Oct. 24, 2000.
Conroy said some of his questions on the IMP had
been answered by Chris Holmes, environmental
engineer for UP Engineers and Architects.
"(Holmes) clarified the land application
rates and the rotation schedule," Conroy said.
"(Rotation) allows the soil bacteria to provide
greater efficiencies on nitrogen uptake."
Rotation prevents saturating the soils of one
area, Conroy explained. Instead of the original plan
to spread the treated wastewater over a two-acre
area, the Jan. 9 IMP calls for five two-acre plots,
each of which will be wetted for two consecutive
days on a revolving schedule, allowing each one to
dry for eight days between wettings.
In their summary of comments and responses, DEQ
officials address the question of the acreage needed
to hydraulically accommodate the discharge, noting
the additional eight acres of land application
results in a land application rate of 25.62 inches
(2.1 feet) per year, or .70 inches per day. (The
land application rate in inches refers to the volume
of wastewater that will be spread over the 10
acres.)
The Jan. 9 draft IMP says, "The spray
irrigation system is a slow-rate process that will
utilize crop uptake and soil matrices to remove
Total Inorganic Nitrogen (TIN). Northern Hardwoods
make up the current vegetative cover and will be
maintained and harvested to ensure forest health and
marketability along with steady nutrient
uptake."
The document states also that monitoring, testing
and maintenance of the system will be performed in
accordance with the (Part 31) Groundwater
Discharge Permit. It adds that Northern Hardwoods can be expected to remove
about 40 lb. of Nitrogen per acre per year and the
system has been designed to allow a loading cycle
that allows time between each loading for the
following:
- soil organisms to decompose organic
constituents in the wastewater;
- the soil to become aerated;
- soil conditions to become unsaturated and
aerobic;
- organic solids on the soil surface to
decompose;
- vegetative cover to utilize available
nutrients provided through the application of
the wastewater;
- harvesting operations to occur at the
appropriate times.
The IMP notes that, since the existing forest has
been selectively cut, no additional harvesting is
believed necessary for the next year or two.
However, a professional forester will be contracted
yearly to make recommendations on selective cutting,
taking into consideration nutrient uptake and forest
health.
In an October 31 letter to the DEQ, Jim Mihelcic,
Michigan Tech professor of civil and environmental
engineering, raised questions on the ability of the
originally proposed lagoon and spray irrigation
system to remove nitrogen and phosphorus adequately.
He concluded the system needed either a larger
lagoon or a larger spray area. The IMP now calls for
a larger spray area; but so far DEQ officials
believe the lagoon area is sufficient, especially
since the wastewater to be treated will be much less
in the summer months.
Conroy noted that, unlike a municipal system
which generates wastewater every day, these
treatment lagoons will have the flexibility to
continue to store it until it meets discharge
standards. The additional time would mean additional
treatment. The effluent can be tested as it is
coming out of the lagoons to determine whether it
meets standards.
The IMP calls for an irrigation season of May 15
to Nov. 15, with a schedule of seven days a week for
26 weeks of the year.
The DEQ made Mihelcic’Äôs letter available to UP
Engineers during their development of the IMP. In
addition, Bob Deatrick, senior soil scientist in the
Groundwater Program Section of the DEQ Waste
Management Division in Lansing, said he would
consider Mihelcic’Äôs comments in his review of the
IMP. Conroy said the comment and response summary
handout consists primarily of responses to concerns
and questions Mihelcic raised in his letter.
An example of this is Question/Comment #16 on the
handout, which states:
"The treatment system may be overloaded with
respect to its ability to remove nitrogen due to low
removal rates in the lagoon, soil, vegetative
uptake, and the low concentrations of natural
organic carbon in the sands."
The DEQ response to question #16 says the IMP
addresses the issue of application rate with regard
to nitrogen satisfactorily, but has yet to resolve a
problem in the length of the proposed discharge
season (May 15-Nov. 15):
"The IMP indicates and calculations confirm
that Total Inorganic Nitrogen is proposed to be
applied at a rate of 64 pounds per acre per year.
Published information regarding the nitrogen uptake
characteristics of the proposed cropping system
indicate that nitrogen can be expected to be removed
at a rate of 40 pounds per acre per year. The
nitrogen present in excess of the 40 pounds per acre
per year may be taken up through luxury consumption
by the crop or may percolate to the groundwater at
an acceptable concentration of five mg/l."
The DEQ comment adds, however, that hardwoods in
the region can be expected to cease nutrient uptake
from the soil by no later than mid-September.
It states further: "This issue has been
brought to the attention of the facility’Äôs
representatives. They have acknowledged the
importance of the matter and are currently working
on a resolution to the problem."
In response to Mihelcic’Äôs concerns about
phosphorus removal, the DEQ replies, "The
Department will condition the Part 31 Groundwater
Discharge Authorization on adequate treatment of
phosphorus to meet a discharge standard of 1
mg/l."
In order to meet this standard, the phosphorus
will need to be removed in the treatment lagoon
prior to land application. The IMP provides for
this, stating, "treatment of phosphorus with
chemicals will occur prior to spray irrigation
discharge."
Conroy said the chemical treatment would
"possibly" consist of adding alum
(potassium aluminum sulfate) to the lagoon.
"It binds with the phosphorus and
precipitates it out as sludge and accumulates in the
lagoon," he explained.
Other questions receiving comments or responses
in the handout include concerns about possible
contamination of wetlands and the Montreal River,
noise and diesel pollution, runoff and erosion from
slopes and the role of soil pH.
DEQ officials note the nearby wetlands and rivers
will not be adversely affected by the discharge
because of the application rates based on removal
capacity of the soils and Northern Hardwoods.
As for possible pollution from diesel generators,
they refer to Part 5, Pollution Incident Prevention,
of Part 31, which provides for methods of inventory
of stored material, procedures for preventing
pollution of surface waters and groundwaters and
emergency clean-up procedures. Noise pollution,
however, is outside the jurisdiction of Part 31.
The Department offers these responses to erosion
concerns: "Slopes in the spray irrigation area
are not excessive. Permeable, medium textured sand
soils will promote infiltration of rain and snowmelt
not overland flow. Spray irrigation can not occur if
standing water is present pursuant to Rule
2204(2)(b)."
Conroy said Deatrick is still looking into the
natural pH of the soils. Since an excessively high
or excessively low pH can potentially liberate trace
elements (heavy metals), the system needs to assure
that these are precipitated out into the sludge,
Conroy explained.
The Part 31 Groundwater Discharge Permit
authorizes the permittee to discharge a maximum of
40,000 gallons per day, 7,000,000 gallons per year.
It will expire five years from the date it is
issued. After four and a half years, the permittee
has to submit an application for re-issuance. The
permit is issued under the provisions of Part
31, Water Resources Protection,
of the Natural Resources and Environmental
Protection Act, 1994 PA 451, as amended (Act 451),
being Sections 324.3101 through 324.3119 of the
Compiled Laws of Michigan and the Administrative
Rules promulgated thereunder.
The Pump and Haul Permit authorizes storing
on-site for transport and ultimate off-site disposal
a maximum of 15,000 gallons per day seasonally
(747,500 gallons per year) in accordance with
limitations, monitoring requirements and other
conditions. One condition in this permit is its
expiration at the end of the construction season of
2001, when the lagoon treatment system should be
completed.
’Äì Michele Anderson
January 23, 2001
|