Please Visit Our Sponsors

Local Calumet weather
 

Click Here For Complete Weather
 

Home
Live Cams
Archives
Government
Calendars
Community
Attractions
Local History
About Us
Contact Us

 

Keweenaw Commentary...See What Everyoneís Talking About!!!!


Click Here For Keweenaw Today Click Here For Keweenaw CommentaryClick Here For Keweenaw Today

Crosswinds submits basis of design  for sewer to MDEQ

This view from the top of Mt. Bohemia  shows the site of the parking lot on the south side of the Lac La Belle Road and  the lodge site on the north side. The sewage lagoons are to be located about a  mile toward U.S. 41 from the lodge site-parking lot area, on the north side of  the road.

MARQUETTE -- Crosswinds Communities has submitted  a revised basis of design for their proposed Mt. Bohemia sewage treatment system  to the Waste Management Division of the Michigan Department of Environmental  Quality (MDEQ) in Marquette. Calculating a possibility of 76,000 skiers by year  five, their design calls for more than 4 million gallons of sewer flow for that  fifth six-month winter season.

UP Engineers and Architects, Inc., state in the  report that they "propose to treat the sewage with a stabilization lagoon system  and a forested upland spray discharge system in accordance with state rules and  regulations."

The design for a peak year five estimates 76,000  skiers over a period of 130 days at 17 gallons of usage per skier per day,  totaling 1,292,000 gallons per winter season. The 50 cabins are estimated to use  300 gallons per cabin per day. That would total 2,745,000 gallons for a 183-day  (6-month) winter season. The total winter design flow for year five would then  be 4,037,000 gallons for the season or an estimated 25,000 gallons per  day.

The report says 3.1 acres would be required for  the projected two lagoons - an area calculated from the estimated 61 lbs. of  BOD, or biochemical oxygen demand. The BOD is the complex organic matter found  in wastewater when it biologically or chemically degrades. It describes the  strength of a wastewater, when that wastewater has the potential to deplete  oxygen once it is discharged into a stream. Thus a treatment plant would want to  remove BOD prior to discharge.

This basis of design does not specify where  Crosswinds intends to put the lagoons. It merely mentions the proposed ski  resort is being developed in Keweenaw County in sections 28, 29, 30, 31, 32 and  33.

However, John Sullivan, senior vice-president of  UP Engineers and Architects, Inc., said today that the site for the lagoons has  been selected.

"The (two) lagoons are approximately one mile  toward U.S. 41 from the lodge site-parking lot area. They are on the north side  of the (Lac La Belle) road," Sullivan said.

According to Randy Conroy of the MDEQ Waste  Management Division in Marquette, the location does not have to be specified  until Crosswinds submits more specific plans in their permit application

"The next step would be to submit plans and  specifications for the (lagoon) wastewater treatment system," Conroy said. "We  want to see (their) overall, long-term treatment design."

Sullivan said the goal is to submit the full  application to the DEQ, including the plans and specifications for the lagoon  and pump-and-haul systems, by August 31. The temporary pump-and-haul system is  planned for the first winter season since the lagoons cannot be completed in  time for the projected opening of the ski resort this December. The basis of  design estimates 44,000 skiers for the first year but does not give details on  expected flow for this year.

Earlier this summer UP Engineers contacted the  North Houghton County Water and Sewage Authority to request their accepting the  sewage through pump and haul the first year. At that time Calumet Township Supervisor Paul Lehto, chairman of that  authority, said even an estimate of 50,000 gallons per week would not be a  problem for the system, which now handles 2.4 million gallons per day and has a  60-million gallon storage capacity for the spring season. The facility is also  being expanded.

While Lehto could not be reached for an update  today, Ken Hyrkas, maintenance supervisor for the North Houghton County Water  and Sewage Authority, said the decision on accepting the pump-and-haul sewage  from Mt. Bohemia would depend on approval by the authority board and the DEQ.  That board normally meets, although not regularly, on the last Monday of the  month, he said.

"(The board) could approve it subject to the DEQ  approval," Hyrkas said.

Conroy said the pump-and-haul permit still  requires plans and specification approval for the lagoon system and initiation  of the lagoon construction. He added the developer may be allowed 30 days after  the pump-and-haul permit is issued to start building the lagoons, even though  they may not be completed before winter. Once Conroyís Marquette office approves  the full plans and specifications, he will process the pump-and-haul  application.

The 30-day allowance could be a condition added  to the permit, according to MDEQ Waste Management Division Chief Jim Sygo, who  had originally wanted construction to begin before the pump-and-haul permit  could be issued.

Sygo said Tuesday, "Now they have provided a  basis for design . . . so theyíve identified what their goals are for Mt. Bohemia.  With that we can issue pump and haul with the condition that construction start  within 30 days."

Before issuing a pump-and-haul permit, the DEQ  will issue a public notice with a 30-day comment period. Conroy said he  understood Crosswinds would be requesting a public hearing toward the end of  that comment period. After that, the DEQ has seven days to review the public  comments.

"I wouldnít expect it (the pump-and-haul permit)  to be issued any earlier than 37 days after the date it goes on public notice,"  Conroy said.

Since the lodge and cabins are all under one  owner, the applicant is treated as a private entity and applies under Part 31 of the state Natural Resources and Environmental  Protection Act 451 of 1994, Conroy said.

The basis of design says the discharge by spray  irrigation will follow DEQ Rules (click on Part 22, Rules Summary) 323.2216, 323.2204 and  323.2205. The treatment system requirements, it adds, follow Rules 323.2230,  323.2231, 323.2232, 323.2233, 323.2234 and 323.2236.

Conroy noted Crosswinds has agreed to apply for  a system to include both the lodge and the cabins.

"We feel their development entails both," he  said. "They want to get going on the lodge immediately . . . They want our  concurrence on the design so that the building inspector will give them a permit  to build."

Conroy said the law requires obtaining  water-sewer permits before the fit-for-occupancy determination can be made by  the building inspector. While the DEQ does not consider zoning in its decision  to issue water-sewer permits, the language of the permit implies the applicant  is responsible for obeying any other laws, including zoning regulations.

He added the permit will say, "This permit does  not relieve the permittee from obtaining and complying with any other permits  required under local, state or federal law."

Ray Gerhart, chief executive officer and  president of Northern Consultants, the building authority for Keweenaw County,  said Crosswinds will have to provide Keweenaw County with the water and sewer  permits prior to the issuance of building permits for any buildings that would  require sewer and water. To obtain permits Crosswinds would need:

  • stamped sets of plans (approved by an  engineer)
  • DEQ clearance
  • clearance from the Keweenaw County Zoning  Administrator.

Gerhart said Crosswinds has not yet submitted  any building permit applications.

"The process begins with the application," he  said. "Until you know whatís going to be built, you canít do a review of it . . . They have to submit a complete application."

Zoning administrator Jane Pelto said today,  concerning the ski lifts, which recently received state approval, that she was  still uncertain as to whether a ski resort can be considered low-intensity and  therefore allowed to be built in a Conservation-Environmental Protection  District (CD-EP). She said the Zoning Board of Appeals has not yet clarified  what low intensity in CD-EP includes.

"I am in the position of not knowing exactly  what low intensity involves. Low intensity could possibly allow ski hills," she  said.

- Michele Anderson
August 23, 2000